Parks/Trails Projects

Updated 3/20/19 - updated information shown in red

Bakersfield Park Restroom
The project includes the installation and construction of a new restroom and additional concrete walkway. The project went out to bid on February 10, 2019. Project rebid due to inconsistent bids received. Currently out to bid again, with plan to award in April.

Bella Lago Master Plan

The project consists of the development of a park master plan for the 9.07 acre park located within the Bella Lago residential development.  The master plan will address the following elements:  site analysis and data collection, opportunities and challenges, public outreach to develop the plans, including preliminary design concept options, a final master plan, and budget estimates.  The professional services agreement, with MHS Design & Planning in the amount of $33,975, was awarded at the November 19, 2018 council meeting. A public input meeting was held on January 24, 2019, at Coram Deo Academy, 4900 Wichita Trail at 7:00 pm. Future meetings planned are:

  • March 7 – Parks Board meeting: Work session included preliminary design concepts and collection of feedback from board and public – complete.
  • April 4 - Parks Board meeting: Public Hearing to consider recommendation of conceptual master plan to Town Council. Postcards being mailed and signage posted in adjacent neighborhoods, as well as social media and website.
  • May 6 – Town Council meeting: Public Hearing to consider approval of the Conceptual Master Plan
Canyon Falls Park Design

This project is for the design of the approved master plan for Canyon Falls Park.  The consultant is currently conducting the site assessment of the park which includes a site survey, including the location of existing trees and topography, soil analysis, and a drainage study.  The site assessment will aid in the proper location of the amenities.  The professional services agreement, with Mesa Design Associates in the amount of $149,500, was awarded at the October 1, 2018 council meeting. The design is expected to be complete by Fall 2019.  The consultant will provide the Parks Board with a design update at the 60% completion mark.  Once complete, the project will be put out to bid for construction in FY 19/20.
Design is ongoing.

Cortadera Park Improvements

The project includes a new interior loop trail that includes benches overlooking the pond, new basketball goals with courtside benches, ADA compliance improvements, and irrigation for the practice field. Additional improvements include a section of wrought iron fencing at the pond and new trees with irrigation.  Construction of the interior loop trail should begin next week.

Anticipated completion: May 2019

Heritage Park – Phase IV 


This project will include an additional eighteen parking places with lighting, concrete sidewalk to connect to the trail, a wildflower meadow with designated areas with irrigation, a plaza area with signage kiosk/sundial structure, a scenic overlook, connection of a nature trail to the east side of the park via stone steps along embankment, an eighteen hole disc golf course and an entry sign at the plaza area and all infrastructure to support these elements. The professional services agreement with Schrickel, Rollins, and Associates, Inc. to provide professional master planning and construction documents in the amount of $147,000 was approved on March 20, 2017. Construction contract awarded to North Rock Construction LLC., in the amount of $1,497,772.95, on March 5, 2018. Disc golf installation is complete. Soft opening was February 22 with grand opening March 30.

Anticipated completion: March 2019

Rheudasil Park Design

The project is for the design of the approved Master Plan for Rheudasil Park (approved December 2014).  Design of the project was delayed until completion of the dredging and bank stabilization project. The professional services agreement, with Studio Outside Landscape Architecture, LLC., in the amount of $136,700, was awarded at the October 1, 2018 council meeting. Due to the length of time since the master plan approval, the master plan was “re-presented” at the December 6, 2018 Parks Board meeting. A design kick-off meeting was held on December 9.  The next step is the site assessment.  The design is expected to be complete by Fall 2019.  The consultant will provide the Parks Board with a design update at the 60% completion mark.  Once complete, the project will be put out to bid for construction in FY 19/20.