Facilities Projects

Updated 3/20/19 - updated information shown in red
  

Central Fire Station Expansion/Renovation
The project consists of an addition to the southwest side of the station, located at 3911 South Broadway, and the renovation of the fire administration area of the building. The work includes replacement of interior lighting, HVAC systems, electric circuits, and flooring. The improvements and expansion required staff to be relocated with administration being located on site in a construction trailer. Ongoing work/installations:

  • Exterior demolition
  • Interior framing
  • Electrical and plumbing rough in
Anticipated completion: December 2019

Fire Station #7

The project consists of an approximately 10,000 square foot Fire Station and associated site improvements located on Skillern Road, just north of the intersection of Wichita Trail and Skillern Road. A professional services agreement with Brown, Reynolds Watford Architects, Inc. for the design, in the amount of $399,600, was approved on February 5, 2018. Kick off meeting held February 20. Design is complete. Construction contract awarded to Schmoldt Construction Inc. in the amount of $4,495,650.00 on January 7, 2019. Groundbreaking was held February 15. Notice to proceed was February 18. Tree clearing is complete. Oncor work next to Coram Deo began during spring break. Poles were placed in incorrect location; being relocated. Contractor work is underway.

Anticipated completion: January 2020

Library Expansion/Renovation

This project consists of a renovation of the existing 25,000 sq. foot Library and an expansion of approximately 15,000 sq. ft., as well as associated site improvements. On December 4, 2017,  a professional services agreement was approved for design services with Komatsu Architecture., for $794,963. Komatsu Architecture was the architect for the library when built. Design is ongoing.  Construction Manager at Risk (CMAR) contract with Steele-Freeman was approved on June 18, 2018. 95% plans received. Construction award planned for April. Site plan  was approved March 20, 2019.

Police Department Expansion/Renovation
The project consists of an addition to the east side of the building, renovation of the Exterior Insulation and Finish System (EFIS) and additional secured parking for vehicles. Contract awarded on August 20, 2018 to Schmoldt Construction Inc., in the amount of $1,525,000. Ongoing work/installations:

  • Paving - 65% complete
  • Exterior electrical
  • Plumbing
  • Pad site
Anticipated completion: September 2019

Town Hall

The project consists of an approximately 46,000 square foot Town Hall and associated site improvements located at intersection of FM 1171 and Morriss Road being the same location of the existing Town Hall. The project will utilize the Construction Manager at Risk (CMAR) delivery method. A professional services agreement with Oxley Williams and Tharp Architects for the design, in the amount of $862,500, was approved on August 15, 2016. A professional services agreement with Kleinfelder Central, Inc., to provide geotechnical professional engineering services, in the amount of $14,990, was approved by Manager Communication on August 28. The Construction Manager at Risk (CMAR) contract with Steele Freeman was approved by Town Council on December 19. The CMAR contract with Steele Freeman, Inc., in the amount of $15,796,695, was approved at the June 5, 2017 council Meeting. Ongoing work/installations:

  • Landscaping
  • Hardscape
  • Punch list items
All staff are moved into the building. Final items being removed from the Atrium building (leased facility located at 1001 Cross Timbers) before end of the lease this month. An open house will be scheduled once all employees are moved and settled into the new building.  

Anticipated completion: March 2019